Marumsco Hills
Elementary School Addition
Woodbridge, VA
Approx. 2.2 million
Job
duration 380 days from Notice to Proceed
Bids Due: Monday,
June 30, 2008 at 3:00 PM
This project is the construction of a
10,700 sf addition and 3600 sf remodel of existing rooms.
The addition has to be permanently
weathered by November 14, 2008.
The work involves selective demolition,
site work, site utilities and paving, landscaping, concrete, CMU w/
brick veneer, structural/ misc. steel and decking, waterproofing, EPDM
roofing, doors frames and hardware, aluminum windows, interior
painting, louvers/vents, athletic equipment, casework, furnishings,
mechanical HVAC & plumbing, fire sprinkler, electrical,
telecommunications and fire alarm system.
Plans will be made available to interested
bidders by contacting Milestone Construction Services, Inc.
Fax: (703)
406-0964
E-mail: smetta@milestoneconstruction.com
Plans can also be viewed online at the
following website after June 16, 2008:
- http://www.mbcpi.com
à PlanWell Enterprise
Login Button à Guest Access à
Project Number: MBCP_ MARUMSCO HILLS. No Password.
<>
|